on 07-22-2008 7:16 AM
Hello Experts,
when I am doing easy Cost Planning the system showing an error "there is no planning element "..where as I have taken child WBS as Planning element .
I have no integrated planning ....Please guide me
Regards
Rama S. Sharma
answerd
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sometimes system doesnt get refresehed automatically, reassign the planning element indicator to the WBS Elements and save the project and retry the Easy cost planning tool.
Regards
Murali