Degree of Processing visible in Project planning board

Former Member
0 Kudos

Is it possible to show percentage completion of an activity in the bar chart of a planning board same as we do in MS Projects.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

From planning board using field selection to add more the column for table view:

Setting -> field selection: add field "Processing % Of Work" to table "Selected Field"

maybe there is no progress bar as ms project

Regards,

Long

Former Member
0 Kudos

Thanks for the solution Long,

I have tried that but in planning board it doesnt give me the desired values.

For example

activity 1 - % of work complete - 10

activity 2 - % of work complete - 10

so at the total at higher wbs it should give me percent complete as 10 after aggregating..

Please help in this.

Regards,

Farhan