How to configure percentage of Completion so that % accumulates at a higher WBS for the project
Its a standard feature availble in SAP, there is no seperate configuration for aggregation of POC. For further details check the following link
http://help.sap.com/saphelp_47x200/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mr. Murali,
Thanks for the solution.
I have gone through all the information in that but i found to calculate or configure POC we need to define statistcal key figure..
That is where i am getting confused with as to why it is required to be done also which method to adopt for POC 20 to 80 or 0 to 100
Regards,
Farhan ( I am new to PS- a new entry)
Selcting the method is very important and it depends on the customer requirement. u can select any one of the following methods.
1) 0-100
2) 20-80
3) quantity prop
4) time prop
5) estimates
6) degree of processing
7) cost proportionality
😎 secondary proportionality
9) milestone technique
Check with ur customer requirement and select the suitable method for planning and actual progress determination.
Regards
Murali