Budget check not active for commitment & actual budget

Former Member
0 Kudos

Budget check runs fine while checking budget limits for Production order and vendor invoices i.e does not allow to further create production order and vendor invoices if budget limits exceeds the released budget.

But this budget check does not work on procurement processes ( PR, PO &GR).

No warning or error message pop out and the system allows to further create PR/PO/GR beyond released budget

What config changes are required to make budget check active for procurement processes.

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

Hi vishal,

Check the Transcation groups in Budget tolerance limits.

PScostsbudget---define tolerance limits.

If you assign ++ All Activity groups it will activate the Budget avaliability control for all Transcation.

Check the avaliability control in OPS9 whether the activation type is 1 or 2 . If 2 run the avliability control CJBN.

Hope this will helpful,

Regards,

former_member563943
Participant
0 Kudos

hi nag,

in tcode OPS9, wat if the activation is set to 0....

is it mandatory to set the field to 1 or 2...?????

regards,

Preeti.P.G