Dear all

During results recording When a result is recorded against a characteristics,in dev normally a window pop up for accept or reject of that characteristic,but now due to some reasons that window is not coming.please give me an idea to have that window so that i can accept a characteristic even result is not within specs

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Presently u are valuating the results automatically.

If u need it manul u have to provide it in the sampling procdedure.

Will u elaborate what result recording this scenario belong to.

Ramesh

Former Member
0 Kudos

Hi Ahmad..,

There was a change in customizations due to this yor are not getting tht popup.

Go to Results recording tab page of "Plant Dependent QM settings" in SPRO.

change the "Recording Configuration" as per your needs.

I hope this will solve your issue. if not come back.

regards.

Former Member
0 Kudos

hi

for that you have to go to sampling procedure QDV1 create sampling procedure with manual valuation.Then assigned that sampling procedure to your inspection plan to your inspection characteristics. then checked that you will asked for accept or reject by with windows