Inspection lot taking Prod version start date

Former Member
0 Kudos

I tried to create an inspection lot thru MFPR, after maintaining 13 inspn type in mat master. I am facing an issue then, its prodn version start date is 01/04/08 and Routing I updated in 01/07/08 with some additiinal inspn chars.

Now lot is getting generated but without inspn chars which are created on 01/07/08 as it is considering only prodcution version start date.

How can I generate lot with my updated routing. Or do I have to create routing with same date as prodn version start date.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Viny,

1 You have created any Master.

2 You have created any order.

3.You have changed any related master to the order.

4. You want to release the Order.

In this scenario you must perform the "READ MASTER DATA" function to incorporate the latest changes to the Order and the other functions related to the Order.

Regards,

Shyamal.