on 07-21-2008 9:15 AM
Hi,
I am currently using PDP channel for backend PR transfer. Once the PR release is carried out in ECC, I am sending the same to SRM, its getting stuck up in SMQ1 (of ECC).
If I check in SLG1 in SRM , I am getting error messages as
1) Select a location to which a plant has been assigned.
2) System status INCM is active ( Shopping cart XXXXXX)
I can understand that it is creating a SC but while creating the the same it's not finding the backend plant and hence status of the SC is INCM.
Can anybody throw some light on this.
Thanks in advance.
Rahul
Hi Nagarajan,
Business partner ID is maintained in the extended attribute of the PDP channel.
Dinesh, the precess is stopped for all the plants. Any other clue?
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pl check the consistency of org structure with BBP_BP_OM_INTEGRATE
also for test purpose
remove the plant BPs from PDP channel ex attributes and give it in ex attribute of corresponding org unit in org structure.
In our implementations we never specified the plant BPs in ex attribute of PDP channel but at resp org units
BR
Dinesh
Yes backend plant are replicated and I have already transfered about 750 PR's successfully.
Is there anything (specially related to attributes) because of which the replication process has be stopped?
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you replicate your backend plants with the report
BBP_GET_LOCATION_ALL
(pl check the syntax)
BR
Dinesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.