How to set transit time, Picking time, Packing time for the required delivery date in Backward Scheduling Process.

Thanks

Mani

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member204513
Active Contributor
0 Kudos

Dear Mani,

Example of Backward Scheduling for In-House Production

Example Data

Requirements date

25.6. (Friday)

Goods receipt processing time

2 days (workdays)

In-house production time for the material:

6 days (workdays)

Opening period

6 days (workdays)

Workdays = Monday to Friday, no bank holiday

Scheduling

Requirements data minus goods receipt processing time = order finish date

25.6. (Friday) minus 2 workdays = 23.6. (Wednesday)

Order finish date minus in-house production time = order start date

23.6. (Wednesday) minus 6 workdays = 15.6. (Tuesday)

Order start date minus opening period = order opening date

15.6. (Tuesday) minus 6 workdays = 7.6. (Monday)

Example of Backward Scheduling for External Procurement

Example Data

Requirements date

31.10. (Monday)

Planned delivery time of the material

10 days (calendar days)

Processing time for purchasing

1 day (workdays)

Goods receipt processing time

2 days (workdays)

Opening period

10 days (workdays)

Workdays = Monday to Friday

Scheduling

Requirements data minus goods receipt processing time = order finish date (provision date for vendor)

31.10. (Tuesday) minus 2 workdays = 27.10. (Friday)

Order finish date minus planned delivery time minus processing time for purchasing = release date for purchase requisition or order start date of planned order for external procurement.

27.10. (Friday) minus 10 calendar days minus 1 workday = 16.10. (Monday)

Release date minus opening period for planned order = opening date of planned order

16.10. (Monday) minus 10 workdays = 2.10. (Monday)

I hope it will help you,

Regards,

Murali.

Former Member
0 Kudos

Hi

Can u tell me which T-Code i have to set this.

Thanks

Mani

former_member396676
Contributor
0 Kudos

Hi,

Please follow this menu.

SPRO-IMG-Sales and distribution-Basic function- Delivery scheduling and Transportation Planning.

Thanks,

Vrajesh

former_member184555
Active Contributor
0 Kudos

Hi

The transit time is specified in the Route and the Pick/Pack times can be specified in Shipping point.

Thanks,