Hello,

in our system, we have defined the price of an item in the price list as 60$ per 1 DZ.

When we make a sales order, the system picks the correct price. But when we change the quantity to 1 EA, the system takes the Nett Price as 4.98.

When we change the quantity to 1 dz, it comes back to 60. when we change the quantity to 2 ea, it takes 9.96.

IF the quantity is full ie. 12 Ea, then the price is ok. when it is less than that there is a difference of 0.02

Any clue on how to solve this...

THanks and Regards

SP Kumar

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi

Promod

U please check the unit of measurement in material master in basic data there u check / define 12 ea = 1 dz. Second plesase check the SCALE of the condition u have maintian PROO. Then u try to create the sales order and check.

Hope this will help you

THX.

Former Member
0 Kudos

Hi Pramod,

It may be the problem with conversion factor. Check in material master the base unit and sale unit and the converstion factor maintained for it.

regards

prasad

Former Member
0 Kudos

Hi

please see the perticular condition type is rounding up or commercial rounding.

In condition type please see the setting of the field value and quantity. and the scales maintained.

thanks

Kuntla

Former Member
0 Kudos

Hi,

Pls clarify, change is happening for one condition type or net price including taxes??

If it is for a particular condition type then check rounding rule to the same.

Pls reward if works.

Rgds

Jack

Former Member
0 Kudos

hi

Please check the material master , base unit of measure , additional unit of measure and the sales unit.