Hi ,
Shipping condition available in customer master and in the sales document type. why two shipping conditions needed. if needed what will be the use of these shipping conditions.
where exactly each shipping conditions are used.
points will be rewarded for the good answer.
thanks
Kuntla
Dear Kuntla
If you dont maintain Shipping Condition in customer master, then while creating sale order, system will propose shipping conditions from Sale document type.
Similarly, if you maintain in both (that is in customer master and sale document type as well), while creating sale order, by default, system will propose from customer master.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kuntla,
If the Ship to party is different from the sold to party your assumption is correct.The shipping conditions will be taken from the ship to party master to detrmine the route and shipping point.
But the ship to party will be entered in the sales order it self based on this all the data will be copied to the deliveries.
I hope Shipping point determination and Route determination are dependents for shipt to party but not dependent for deliveries.
I hope it will clear for you,
Regards,
Murali.
Still exact answer i did not find for this thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Kuntla
Reason-1
If you maintained shipping conditions in:
Sales document type (vov8) and Customer master data (from ship-to-party only).
System always should be taken from Sales document type (vov8).
1) Sales document type (vov8)- This is applicable for all sales orders which mens irrespective of customers.
2) Customer master data (from ship-to-party only)- This is only for puticular customer.
Reason-2
1) Sales document type (vov8)- This customization seeting is only in IMG part, which means user couldn't do this.
2) Customer master data (from ship-to-party only)- users can autorised to change it.
Reason-3
Q) Why use both areas means: Sales document type (vov8) and Customer master data (from ship-to-party only).
Ans) To determine deffernet shipping points (using differnet shipping conditions)
Note:
If you maintained shipping conditions in:
Sales document type (vov8) and Customer master data (from ship-to-party only).
System always should be taken from Sales document type (vov8).
Thanks & Regards,
Hari Reddy.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi guys,
always Shipping condition which is maintained in Sales doc type will override the Cus mas Ship condn.
this is provided to capture the following scenarios
1.when you do return process,System will pickup diff Ship.point
2.if you do the Rush order sales, system will pickup diff ship. point
thats,' all
veera
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Gopal,
The shipping conditions are proposed by the customer master record. Should an entry have existed in the doc type config(VOV8), this entry would have taken precedence and overwritten those found on the customer master record. The shipping condition value is used to determine the shipping point.
Shipping points are determined based on Delivering Plant(in SO)+ Shipping Conditions(as explained above)+Loading Grp(from Material Master).
And the delivery process originates from Shipping Point.
I hope this is enough information.
Rgds,
Raghu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hI,
NO I DONT AGREE WITH LAXMIPATI.
system will first give the priority to Document type, if there is no shipping point maintained ,then only it will search customer master.
we can maintain two different shipping conditions , because we can change the shipping point in sales order
cheers
reward if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kuntla,
If you don't configur the shipping conditions in the document type system will take the shipping conditions from the customer master.
If you configur the shipping conditions in the document type
The system proposes shipping conditions from the customer master record.
The proposal from the customer master record is overwritten by the
shipping conditions that you define for a particular sales document type in Customizing. The entry from Customizing is considered as a default
value.
If no shipping conditions are set in Customizing for the sales
document type, the shipping conditions of the sold-to party are used.
Shipping condition in both places will be used commonly for
-->Shipping point determinatuion
-->Route determination
I hope it will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.