why the basic date is changed when save the project.

Former Member
0 Kudos

now wbs have his own basic date.

network also have his own basic date.

activity also have his own bais date.

when save the project, the basic date of WBS, network, Activity is changed.

now the user's request is :

the basic date can't be changed.

Please explain me all the steps to be required.

Thanks in advance!

now the customizing is below:

WBS scheduling prof. : Scheduling type: 3 olny capacity requirement

Schedul. method: network determines dates

Adjust Basic Dates: NULL

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

dear kindly check the t code opu6. there are 4 options for adjust basic date select last two one whch will meet your requirements.

3. The basic dates are adjusted and the dependent requirements are scheduled for the order basic start date.

4. The basic dates are not adjusted and the dependent requirements are scheduled for the order basic start date.

i HOPE the problum will be solved

reward points

usman

Answers (0)