Bolcking posting in WBS element

Former Member
0 Kudos

Hi All,

Let us suppose there is one project which has 4 WBS levels.

Lelevel 4 has account assignment element and level 3 also.

Then the requirment is user do not want to cost booking in level 3 but in only level 4 only. When i am trying to removing acccount assignment in level 3 , system is not allowing to do that.

Can anybody help me on that. How can we restrict to user so that they can not post cost in level 3.

Regards,

Ravindra

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

Hi ravindra,

In Project profile OPSA remove the indicator All Acct Asst Elem in control tab and check.

Regards,

Former Member
0 Kudos

It is allready deselected.

Is there any other way to do that.

Regards,

Ravindra

Former Member
0 Kudos

In CJ20N, select the WBS goto Edit->Status->Lock->Acc Assignment