Dear All

Can anybody tell me how to aasign equipment to WBS after creat equpt in IE01

Regards

Prathamesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can mention the WBS element in organisation tab of the equipment master data. The integration aspect is below:

When you create a maintenance order for this equipment, based on the configuration settings the PM Order is automatically assigned to the WBS which ever is mentioned in the equipment master data.

Once you've got the order assigned to WBS, you can use the WBS budgeting functionality apart from scheduling etc.,.

Regards

Sreenivas

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi prathamesh narkar ,

Go to IE02 and in the organisation TAB , you can assign the WBS Element.

Cheers,

Sanju..

Former Member
0 Kudos

Hi,

You can attach Equipment in the assignment tab of the WBS details screen.

Also you can define Equipment as Work center thru CNR1 and attach itto the internal activity.

Rgds

former_member203098
Active Contributor
0 Kudos

Hi prathamesh,

You can assign equipment for WBS element in ASSIGNMENTS TAB.

Regards,

Former Member
0 Kudos

Hi Pramatesh,

As far as i know we cannot assign an equipment to WBS.

WBS is defined as a settlement receiver in the settlement profile for a Order type.

Orders made using this order type for an equipment will have WBS as a settlement receiver.

Further you can define the WBS as account assignment in the Organization Tab of the equipment.

Why do you want to assign the equipment to WBS.I mean what is the Business scenarion , please clarify