on 01-06-2006 10:03 AM
Dear All
I want to default the values If we want to keep IT0016
(Contract Elements)/Subtype - Expiry of Probation ( Set as 6 Months) and when it comes to IT0019 ( Monitoring of Tasks )i want system to default the Date .
The system will default the date but my requirement is the date should be (If an employee joins Between 1 to 15 the confiramtion date should be defauled as 1st and if it an employee joins Between 15 to 30 the confirmation date should be defaulted as 15th )
I know dynamic action is the only solution can anyone help me to write a program for this as i am in the functional side.
Regards
Raji
Thanks suresh
I dont know where to go and Reward the points
Regards
Raji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raji,
This can be done very easily by writing a small Sbroutine Pool Program, and call it from Dynamic actions..PL take a look at the program RP2006P0 to get an idea .
Regards,
Suresh Datti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.