on 07-16-2008 10:51 AM
Hi all,
Does anyone know if there is there a report that will show the number of hours booked for labour against a project and that also shows a breakdown of the labour costs?
Many thanks.
Hi,
try CADO - Time sheet report .
- Satish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CJI3 - Line Item report can show you those values provided you include the fields Quantity, Personnel Number etc., in the layout.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |