on 07-16-2008 12:59 AM
Hi all,
I've tried to find something about this issue at this forum, but no consistent response was found.
Now i've a serverX with SLD and all NWDI components. And in this we have many products and software components already developed. We need to change the current NWDI server to another serverY. Does anybody has a reference to migration procedure?
Best Regards
Isaías Barroso
Isaias,
take a look at SAP Note No. 877029
This note describes how the NWDI related components (DTR, CBS, CMS) can be moved to another host by using the System Copy Tool.
regards,
Kentaro