hi all,

Is ther any way of changing company code on a WBS element?

an urgent issue...

regrds

pushpa

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can't change the company code if any financial postings are already taken place against that WBS element.

Thanks

Kishore

Former Member
0 Kudos

hi kishore,

you mean after settlement has been done for order....

regrds

pushpa

Former Member
0 Kudos

hi ,

i meant when WBS has been settled....

regrds

pushpa

Former Member
0 Kudos

Settlement come in to pictuire in the later stages. But once any actual costs are booked against particular WBS element, those costs will be accounted in the corresponding company code accounts. So u can't change ur company code in ur WBS element after that happens.

Example for actual costs cud be : GR against ur project POs for non stock materials/GI against activities or reservations of ur project/direct financial posting like vendor invoice postings against project etc...

Thanks

Former Member
0 Kudos

hi kishore,

i am new to PS

IN our project we r getting budget from IM , now i tested in this way i have created new WBS in proj and now i am able to change company code , nd after allocating budget to tht WBS i checked in CJ20N wher WBS company code is greyed out...

give ur inputs on the same....

regrds

pushpa

Former Member
0 Kudos

Sorry.... Even budget transaction makes it greyed out at WBS level....