Settlement of amount from Lower level WBS to Top level WBS

Former Member
0 Kudos

Hi Friends,

I have certain amount on my 2nd level WBSE. I am getting an error when I am trying to settle this amount to the Top level WBSE which says "Budget was exceeded by 2,000.00 INR in document item 001 WBS element TEST321" where TEST321 is my top level WBSE and 2000 is the amount.

I think I have set the settlement rule on the 2nd level WBSE correctly.

Please help.

regards

Pratap.V

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

One option, if you are settling using settlement by settlement cost element, add this cost element to be excluded in availability control using T Code OPTK.

Your settlement rules are just fine but it's to do with activated availability control.

Also refer note 159850

Regards

Sreenivas

Former Member
0 Kudos

Done Sreenivas. Now it is ok. Can you just explain some more about this process as to why I was getting the error?

regards

Pratap.V

Former Member
0 Kudos

Refer the OSS note mentioned in the response.

Regards

Sreenivas

Former Member
0 Kudos

Ok thank you. I will close the posting.