Hi Gurus!

While Creating WBS element for CAPITAL, the Cost Centre field should be Mandatory field-How to configure the same?

Thanks in Advance. Its an very Urgent Issue and waiting for the immediate reply.

Regards,

Nageswar Rao Jalla

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

This message was moderated.

former_member203098
Active Contributor
0 Kudos

Hi,

Check in T-code OPUK field selection for WBS elements. there you can make the cost center as required field.

Regards,

Former Member
0 Kudos

NAG,