Hi all,
We have implemeted Clasic scenario and we have local contracts in SRM. Now we want to create PO in R/3 with this contracts. Is it possible to create PO in R/3 with SRM Contracts? What are the customizating settings we need to do?
Thanks
Ravi
Hi Ravi,
with local SRM Contract you cannot create a PO in ECC with reference. How should ECC know about local documents in SRM?
You need to make the settings to directly create the contract in ECC by implementing BADI Be_Contract_Create. Then the contracts are created not in SRM, but in ECC and can be used.
Cheers,
Claudia