Dear All,

I am executing CJ88 transaction for one wbs element for doing capitalization.

But system is giving following error message.So i am not able to do the capitaliztion.

Error message details as follows.

SYST: Abnormal termination (ANLB-LGJAN not equal to ANLC-GJAHR) Asset P1100009010059220000

Message no. AA698

Asset affected: 000901005922-0000

Diagnosis

Processing terminated due to a system error.

System Response

Internal tables ANLB-LGJAN and ANLC-GJAHR of asset P1100009010059220000 are not synchronous.

Procedure

Contact your system administrator.

Can any one help me on this issue.It's very urgent.

Thanks in Advance.

Regards,

Sandeep Theurkar

Accepted Solutions (0)

Answers (1)

Answers (1)

stheurkar
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

Check for the fiscal year where the annual values are already settled in Asset Accounting and the fiscal year of Asset Value fields. There is a mismatch between these fiscal years which is causing the terminations.

Can you please check on the above lines? Also check in for the Assets in AS03 on the fiscal year else some asset reports like AW01N ( T.code)