Hi,
Our Projects are assigned a Budget profile with the following settings:
Activation Type 2 Usage 1.00
Overall - X (ticked)
Releases - (not ticked)
In define tolerance limits, the settings for the budget profile are:
Tr Grp - 00, Act - 3, Usage - 100
Tr Grp - 01, Act - 3, Usage - 100
When I am creating a service order, with a WBS element assigned to it (Additional Data tab page), system is allowing me to create PRs in the service order (for text items), even if the PR value exceeds the budget assigned to the WBSe. I have reconstructed availability control (CJBN). Also checked that the cost elements are not exempted from AVAC. Even then the system is not restricting the PR creation.
My query: Is this a standard behaviour for the above settings? If the system is to give a budget check error while creating the PR, what should be the settings?
Would appreciate & reward appropriately a quick reply
Rgds
Deepak
Hi,
Usually we use Activation Type 1.then AVAC gets active when you do Budgeting.
if you are not getting expected results then ,you can check in Transaction OKKP , whether Commitment Management is set to Active status for your Controlling Area.
Try This.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the note: [166394|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=166394]
Thanks,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
could you double check the WBS system status if it already has BUAP and AVAC?
sometimes budget has not been maintained so AVAC cannot be activated. thus, the effect of this is that if you create a project and release it, if you do not maintain a budget (CJ30), you can proceed with PR, PO etc.. and even incur actual costs even though there is totally no budget at all..
i dont know if we are thinking same scenario..
regards..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi deepak,
As per the costomising settings you had done system
will behave
1. availablity control should be activate for overall budget.
2. Exceeding Tolerance limits in PR and PO 100% system triggers error message.
Kindly check the commitment managment is set active in OOKP controlling area.
Check the operative indicators for WBSE from cj20n account assignment indicator has set active.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi NAG/Nitin,
Thanks to both of you for your replies.
The committment management is active for my controlling area. I had reconstructed the AVAC using CJBN. Also the WBS element is of course with Account Assignment tick, else I wouldnt have been allowed to assign it to the service order (Note: I am assigning level-2 WBSe, which is account assigned, whereas the level-1 is not a/c assigned). Even then the system is not giving error message on the PR value exceeding the budget. Strangely enough for other projects with a different budget profile with Activation type-1, it is working perfectly fine.
Can anyone find a clue from the above info?
In the meantime I will try to check again with giving a tick to the level-1 WBSe in the A/C assignment field.
Rgds
Deepak
Hi Deepak,
If Activation type - 2 is used then avaliablility control will activate after running the project in t-code Cjbn.
We can activate this job in background also.
Hope this will help .
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.