on 07-10-2008 9:39 AM
Dear All
We are looking for a solution wherein we can plan for the QM workload based on inputs from MRP and then do a detailed scheduling based on the firmed production plan.
My understanding is that this functionality is not available in ECC 6.0. Is that correct?
Is there any third party tool which will cater to this requirement? Any of you have any experience in catering to this requirement?
Thanks & Regards
Girish
Hi,
Use work center usage 009 ( all task list) then try to assign it to operation in master recipe.
Sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
User trasanction C202.
Sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
QM work center will be created same as production work center using transaction CR01 transaction. Activatge finite scheduling indicator while creating work center.
QM work center will be assigned to master recipe in same way as production work center, while choosing make sure the capacity planning indicator is ticked .
sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Standard QM module does not provide workload planning for QM work center . You need to write a custom program to do a workload planning. Other option is you assign QM work center to routing or master recipe , work center will be loaded when production order is released .
Sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.