on 07-10-2008 4:10 AM
hi to all,
can anyone tell me how to allow activation of availability control for projects with crtd status only?
currently, i am only able to activate availability control only if i have already done budgeting.. but i want to know if it is possible to do it even if i have not yet done any budgeting..
thanks in advance..
Ekta
thanks..
however still, i need to have a budget (using CJ30) before the availability control can be activated even in the background..
is it possible that as soon as my project is created, i can already run availability control (CJBV) and activate it for the project even if i have not yet done budgeting in CJ30?
because currently, if i run CJBV before doing CJ30, it says "availability control not activated"
thanks in advance..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ekta,
As I know there is no Procedure to activate availabilty for budget in this case .
As I understood your requirement in this case you can keep a Status for budgting(Like CRTD for creation , ORD for Order and EXE for Execution), allow the budgeting in status ORD and prohibited for EXE.
In this cas a person who is handling project keep remember to budget the project ..............
IFI will find any clue of to solve this issue according to your requirment I will send you .
All the best ,
Regards
Rama Shanker Sharma
Hi Ekta,
You can do this bye using Back ground Activation of Availabilit in Budget Profile (OPS9).
Set Activation Type 2
The system activates availability control automatically for all projects/orders in which the funds commitments exceed the usage figure entered in the budget profile. To this end, you must enter:
the quantity of projects/orders for which availability control should be activated using background activation
the periodicity of the background job which activates availability control
Usage in % for background activator
The "credit limit used" expresses the ratio of assigned funds to the budget as a percentage.
This value is used only in combination with activation type 2:
If the background activator determines that this value has already been exceeded by too high assigned funds, availability control is activated for the object in question (project/order).
Example
An entry of 80% means that the background activator activates availability control as soon as assigned funds amount to more than 80% of the budget.
Rewards Point if useful
Regards
Rama Shanker Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.