Converting Valuated project stock to Non Valauted

Former Member
0 Kudos

Hi

I need a clarification on Valuated project stock/Non Valuated Project stcok.

3 Projects are running as a Valauted Project stcok.

Now Client wants to make it as a Non Valuated stock to transfer the material to some other project.

Let me know the option to change it as in Project Defination it is graeyed and its not possible.

Regards

N.Raju

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

After saving the project, u can't change the option from 'Valuated project stock' to 'non valuated stock'.

If u want to use the materials of one project in another project, by transfer posting with movement type 415Q u can do that..

Thanks

Kishore

Former Member
0 Kudos

Hi Kishore,

I agree the movement type which u have given.

Client even insisting to have nonvaluated stock with the same projects which are running.

Let me know, is there any possiblites to do that.

Regards

N.Raju

Former Member
0 Kudos

Hi,

It is not possible to configure both valuated stock & non valuated stock in a single project.

Thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

You can copy existing project via CJ20N to a new one and change the setting for project stock before saving.

However we ran into problems with cost reporting when using non-valuated stock. The costs just dont show up.