on 07-08-2008 9:44 PM
Can any one help me with the report which takes the Work centers as the input for pulling different parameter in the system. I would really appreciate early response.
Thanks
Points will be rewarded.
Hi MKR,
In CR60 we can choose layout and select WBSE and network.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi MKR,
we can get Work center wise report in T-code
CR60 and work center list in CR05.
Hope this will help,
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi MKR,
Can you pl elaborate what do you mean different parameters in the system?
Rgds
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepak,
In my case, Work centers are used as a person and have been assigned to internal activities. CN41 gives the structure of the project to the activity level shoving what Work centers are assgined to. Is there any way that I can pull a any report by Work centers instead of giving a project or WBSE.I would really aapreciate if you know any report that can be pulled by work center.
Thanks
Edited by: MKR SAP on Jul 9, 2008 3:19 PM
User | Count |
---|---|