hi all,

i copied a new service order type from sm02 (customer service). i am creating a new service order and confirming for activity. but activity cost is not appeared on service order. what will be the reason?

(when i use sm02 with the same data, there is no problem)

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

are you taking about the time confirmation or service entry sheet confirmation ,

also whether you are getting the planned and actual cost for order in cost tab page

regards

thyagarajan

Former Member
0 Kudos

time confirmation for getting actual cost.

former_member187991
Active Contributor
0 Kudos

hi

check in the IMG settings you have maintained the costing variant for planned and actual cost

regards

thyagarajan