on 07-08-2008 2:26 PM
Hi all,
Can any body tell me how to stop
automatic PR creation from PS network activities
for a particular project only or projects using particular
cost centers.
thanks and regards
pv
You can control it using a parameter in 'Network Profile'
Create a network profile in the SPRO with field 'Res./Purc. req' set to '1' (Never create a PO).
Assign this network profile to your Network or at the project profile to control the PR creation.
Regards,
Ramesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramesh,
Thanks for the information give you points for that
comming back to my quest.
i forgot to add the point that the project
is under closing stage.ie already activites are released
and PRs are generated.
Now user should not generate any more PR for that particular project only.
Thanks and regards
pv
Standard solution:
There is no specifi status that prevent from entering the WBS or Network activities as being entered as an Account assignment for PR or PO.
But it is possible to set status lock the whole Project which will prevent from any PR or PO created automatically. But unfortunately it will block all the other transactions like confirmation etc.
So it will be like everytime you unlock to do any further transaction on the Project.
-
Custom Solution Available :
Another way is to create a 'user status profile' and 'user status' and prohit the transaction RMBA
RMBE in transaction BS22 to avoid any creation of PR and PO.
Regards,
Ramesh.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.