Budget exceeding error message coming up at the time of GRN

Former Member
0 Kudos

Dear Guru's

I am facing a problem at the time of GRN, When i am going to create GRN to purchase order then message is coming up budgut exceed.

Regards,

Vishal Kr. Sharma

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In Customising

PS-> costs-> budget-> define tolerance limit

you specify availability control activity groups.

Here you specify which groups you want to include for budget checking.

If you specify '++' all activity groups, budget will be cheked for all including Purchase requsition.

SSanjay

Answers (1)

Answers (1)

Former Member
0 Kudos

Or you can increase i.e. add supplement to the Budget for the PS from transaction CJ40 to the WBS element

Regards,

Ramesh-