Dear All ,

here we have one query :

material X , common in plant 1000 & 2000 .

in plant 1000 we have division 40 , created sales order and partially delivered , after partial deliver i have changed division to common 00,

now is it possible to deliver the remaining partial ?

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Venky

First of all you should be aware that if you change the Division in basic data 1 for plant 1000, it will change for plant 2000 also

Second, in order to do further delivery,

- Assign the division 40 to 00 in VOR2

- Assign the sales area in OVAZ (with cross division 00)

thanks

G. Lakshmipathi

Answers (1)

Answers (1)

former_member204513
Active Contributor
0 Kudos

Hi Venky,

If the same material and customer is maintained to 00 devision also ,you can deliver other wise you can't.

I hope it will help you,

Regards,