on 07-03-2008 8:37 PM
Hi experts,
We want to create new prices for coming fall season.
In preparation for this we want to create condition records from existing records but want to change only validity date.
How to work on this?
Thanks
Go to transaction VK34.
Let says you want to copy material price record.
execute material price.
select the condition records
click the copy button at the bottom of the screen and then click execute.
choose change validity.
change the validity period as per your requirement.
choose copy date.
save the new condition records.