Hi experts,

I have multiple condition records. I want to implement a price increase for the new condition records which were created earlier.

Is it possible to change prices simultaneously?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You have not mentioned any details like whether you want to increase prices of materials and by what percentage you want to increase.

Let's say you want to increase prices of materials by 2%.

Go to transaction VK32.

Execute material price and enter material numbers you want to change.

Ensure that the date in the valid on field falls within the validity period during which you want to execute the price increase.

select the condition records.

choose the change amount.

Enter 2 the percentage field and choose copy condition.

return to the previous screen and then save the changed records.