Dear All,

In my project scenario, having two wbs elements with two diffrent comany codes & two diffrent business area which falls under one company.

In this i have to transfer project stock from one wbs to another wbs element.

With above mentioned condition is it possible to transfer the project stock.

Kindly confirm me & also give a procedure for transferring the stock.

Thanks in Advance.

Regard's

Sandeep N.Theurkar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I think it is possible.. im not sure if we have same scenario but we did something similar in previous project...

reservation is done in one project but the plant indicated belongs to the other project. and the transfer type (goods issuance) done is project to project kind of transfer(Movement type 221Q).. the two projects belong to diffenent company codes and business area but same controlling area..

regards..

Edited by: Ekta Gurudutt on Jul 8, 2008 5:21 AM