My requirement is as follows:

I have a stock of 100 PC in my plant storage location. I reserve 50 PC for a sales order number XYZ already created. I have used transaction code MB21 for creating the reservation, the movement type being "231" for sales order.

Requirements:

1. The system should reduce the stock quantity in the unrestricted part by 50 PC so available stock will be 50 PC.

2. I want that when ever the sales order is delivered the system should consume the quantities from the reservation part so next when I see the MMBE report, there should be "zero" quantity in the reservation part.

Please guide me as to how should I configure to fulfil this requirement.

With best regards,

Allabaqsh G. Patil

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

No Answer.

Former Member
0 Kudos

Hello Allabaqsh,

check txn OVZ9, for the avlbly checking grp and rule combo, you might have to check the 'Include Reservations'.