Hi All,

I have a project only with WBS elements (no networks/activities). I created Pur Req with acct assignment 'P', i am seeing the PRs as a commitments.

How can see assigned PR values as my plan costs in the project ? any config needed ?

Please help.

-San

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

closing

Former Member
0 Kudos

As you are not using activities, assigning material to project and thereby deriving planned cost is ruled out. Hence you will have to go for manual cost planning ie CJ40. As per my knowledge you cant transfer commitments to planned cost. There is no such config available.

Regards

Former Member
0 Kudos

u can have purchase order price as planned cost.

transaction opl1

new entries

valuation variant

strategy sequence 1. L from purchasing info record

sub strategy sequence

9. Effective price from Purchase order

transction nOPUV

enter the costing variant plan