on 07-03-2008 5:31 AM
Hi All,
I have a project only with WBS elements (no networks/activities). I created Pur Req with acct assignment 'P', i am seeing the PRs as a commitments.
How can see assigned PR values as my plan costs in the project ? any config needed ?
Please help.
-San
closing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As you are not using activities, assigning material to project and thereby deriving planned cost is ruled out. Hence you will have to go for manual cost planning ie CJ40. As per my knowledge you cant transfer commitments to planned cost. There is no such config available.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
u can have purchase order price as planned cost.
transaction opl1
new entries
valuation variant
strategy sequence 1. L from purchasing info record
sub strategy sequence
9. Effective price from Purchase order
transction nOPUV
enter the costing variant plan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.