Automatic creation of Production order through Project

Former Member
0 Kudos

Hi all,

Could you pls explain how we can create production orders automatically through a project

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sravan ,

Production order Creation steps are given below-

1. assing the BOM to WBS

2.Explode the BOM

3.Reservation will be made

4. Run MRP

here MRP decide for which material you want to make external Purchase requistion /Planed Order

5.On the Behalf of Planed order Production Order will be made.

Rewards points if useful

Regards

SMITH

former_member143179
Participant
0 Kudos

Dear Mr Smith / Rama Shanker

I have read the reply posted by you and is very usefull . Can you please tell us the Tcode to be used for the mentioned steps in your reply .

Also kindly help me on the following requirement .

In our business scenario we have to define seperate budget for Material procurement and seperate budget for Manufacturing expenses . To achieve this , one posiible option can be that Purchase Requisition (for Procurement) are generated in reference of one WBS element and PR for production order are generated in reference of another WBS element . But as FERT (material with BOM) is assigned to aan activity in one WBS element then during MRP run all requirement (PR plus Production Order) will be in reference of the same WBS . So how can we distinguish between them .

Or there may me some other alternate option which we are aware off .

Kindly help us . We assure to award full points for the suggested solution pl .

Rgds

B Mittal