on 07-02-2008 12:30 AM
Hi Experts,
I am working on a bill of material scenario where pricing happens at sub item level and not at main item level.
What configuration setting or changes should be done so that pricing can happen at sub item level in the sales order?
Thank you
If you want pricing to occur at sub item level, change item category group to LUMF in material master record for main & sub items.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To ensure all the components can be delivered at same time, use the functionality of the delivery group.
To check this aspect check the item category determined for sub item level pricing which would be TAP & TAN.
Under section Bill of material / configuration, in the field check delivery group assign X or A as per your requirement.
Now recreate your sales order and see whether you have same schedule lines.
If a delivery group is assigned to the item category of the sub items, the system will determine the latest schedule line of the items and confirm the delivery date according to that last schedule line.
For example if system determines schedule line dates as 4th July, 8th July, 9th July then delivery date would be confirmed for 9th July.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.