on 07-01-2008 11:11 PM
Hi
I have a master recipe with a secondary resource assigned in the phase, this has been ciffed to APO and the secondary resource is visible in PPM inside Mode.
Also, the secondary resource is selected for finite scheduling and the settings are maintained in the resource as well as in the strategy profile.
Now, when I take a CTM run, then the plan is generated considering the availability of the primary, but when I try to reschedule these orders, then order are scheduled even during the non working time of the secondary resource. I am using reschedule heuristic or sometimes manually scheduling these orders in DS board.
Kindly Advise.
Regards
Manoj Narain
Hi
Pls look at the strategy profile. Check whether Non working times has been ticked . If so, then de select the same and save
Hope this helps
regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.