Hi Experts,
when i assign a revision in the order, its start and end dates are changing according to the revision dates.
But when i assign some operations and define the time for them and when i save the order, system do the scheduling of the order and it changes the order start and end date accordingly.
So what could be the possible solution, so that the revision dates are not effected by the order scheduling date.
Regards
Pankaj Verma
hi
if you dont want to adjust the dates according the operation dates ,then you have to make the scheduling parameters as Donot adjust basic dates,dept reqmts to operation dates.in T code OPU7
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thyagarajan,
Thanks for you clear explanation.
I want some more explanation on the below help given in sap: if you can elaborate a little bit on this
"There are the following possibilities:
The basic dates are adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.
The basic dates are not adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.
The basic dates are adjusted and the dependent requirements are scheduled for the order basic start date.
The basic dates are not adjusted and the dependent requirements are scheduled for the order basic start date.
Here i think basic date are order Basic start date and Basic finish date. But what is the meaning of dependent requirements.
Regards
Pankaj