Automatic creation of PM order by a project

Former Member
0 Kudos

It is possible to automatically create a PM order on a Project?, I already have the configuration to link PM orders to a project.

If so, please give me a tip for it.

Best Regards...

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Iam sure that PM orders cant be created automatically thru project ( Standard SAP does not allow this. ) , however we can link the PM order to a project.You can create PM order thru IW31 and can assign a WBS there.

Reward points required, if this answer helps you a little bit .

Regards,

Dhruv Kumar Malhotra

Answers (2)

Answers (2)

Former Member
0 Kudos

One project type needs the services of maintenance personal, this personal is on maintenance Work center.

The user wants to create the maintenance directly from the project with a simple process, without creating the maintenance order on PM.

The want something like the process to create PR with MD51.

Best Regards...

Former Member
0 Kudos

Hi Juan,

You can do it by linking a Maintenance Plan and Milestones.

create Maintenance plan cycle

Create a mile stone in your project.

Trigger a milestone function module.

Inside the function module call the function module to tigger the maintence cycle with will create the MO when the milstone is triggered.

You can also explore variant configuration for doing this.

Regards,

Ramesh

Former Member
0 Kudos

hi jaun,

plz explain your scenario requirement.....

regrds

pushpa