Hi,

We need that when we record calibration result, system should stop me if expiry date of master is in past.

Master is maintained in the task list as a material PRT.

This material is managed in batches.So we will have more than one batches for a single PRT material and those will have different expiry date.

We want to assigned a material PRT batch as a master in the task list. but when we go to assign material PRT in the Task list , there is not field for the Batch.

Pl suggest me how we can overcome with this Issue.

Thanks in advance.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member206980
Active Participant
0 Kudos

solved

Former Member
0 Kudos

Hi,

Assign the material with serial number now activate its equipment view.

In equipment view u will find the gurantee field which u can assume work around for your requirement.

Ramesh

former_member206980
Active Participant
0 Kudos

Pl share your view regarding above context.

Regards,