on 06-30-2008 12:21 PM
Dear All
My client has asked me to show them S-Curve graphical presentation.... I am not been able to get the proper shape of the three curve.
My second question is..I am having problem in internal Activity confirmation.. I use my work center with planned activity type, i have confirmed that activity but no actual cost is coming on the activity or respective WBS, neither its going into the cost center given in work center master data.
Please assist me
Asif
Hi,Asif Iqbal
I am watching your another question about Project Progress (EVA).But now that topic has been locked and I couldn't reply to that. I hope that it is helpful and needful.
We know that:
1.BCWS = Planned POC * overall costs
2.BCWP = Actual POC * overall costs
so,we must make sure the POC has been setted in the active and confirm it.(CJ20N)
Run CNE1,I think you may get the result in CEN5.
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Asif: For activity costing, you have first plan the costs using kp26. Then calculate costs on the network activity.
Please reward points if helpful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.