on 06-28-2008 10:18 AM
Hi Experts,
I have a problem, I have to change base unit of one material. No transaction has been made in any plant. But when I change base unit of measure from Nos to Rol. Following message is coming.
Routing already exist, that are assigned to material.
Type Q, Group - xxxx, Grc - 1, Plant - 1000,
I have deleted inspection plan thru t-code QP02 and also de activated Quality in MM02.
What should I do.
Please help me.
Full points for helping answers.
GR
Hi G R,
First off all, delete the material assignment form the routing.
Then go to table MAPL and delete this assignment entry from the table also and then try to change the UOM.
Hope it may wrok for you.
regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.