Capacity planning for Work Center

Former Member
0 Kudos

I programmed time for a Work Center on internal activity, for 40 hr using 100% of one resource, the work center it has a capacity of 8 hr each day, the activity gets a duration of 5 days and I indicated that it has to begin the first day of the next month.

When I executed transaction CM01, I notice that the 40 hours are planned for the actual day and don´t respect the dates of the internal activity, I think it is a problem with the work center but do not find the error.

Any suggestion where to look for?

The data used for creating the Work Center on Capacities:

- Capacity Category : 002 Person

- Other formula: SAP008

The data used for capacity:

- Base unit of meas.:H

- Start: 08:00:00

- Finish: 17:00:00

- Capacity utilization: 100

- No. of indiv. cap.:1

- Unit: H

- Relevant to finite scheduling: active

- Can be used by several operations: active

- Long-term planning: active

The data used for creating the Work Center on Scheduling:

- Capacity Category: 002 Person

- Other formula: SAP004

- Work dimension: Time

- Work unit: H

Best Regards...

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please activate the capacity requirement in Capacity tab in CNR2.

Thanks..