Hi Experts...
I'm using the program BBP_EXTREQ_TRANSFER to make the PR replication from R/3 to SRM. The program it works, but when i have a actualization in PR (R/3) that already was executed by the program, the modifications doesnt get in SRM.
For Ex:
PR 0001 ( this PR was replicated by the program, Can i make in SRM as SC)
I have a modification in this PR, including the new item, after a executed the replication program again. But the new item dont get in SRM.
Is there any way to make the replication for modifications in PR?
Thanks,
Hi Kristin,
By satndard, PR change should flow to SRM if configuration is correct. In EPRTRANS table a new PR document entry is saved with status "1" and PR change is saved with status "2".
Ensure that you done all setting as per note 656597. If you don find clue, escalate the issue to SAP OSS support.
Regards,
Prashant
Do reward points for helpful answers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.