cProjects Automatic MLC: Time unit is empty

Former Member
0 Kudos

Hi Experts,

When trying to do the automatic MLC on cProjects we get the following error in the controlling cockpit: Final check of the project definition and the WBS elements: Error

When I check the extended error I see that the failure is "TIME_UNIT is empty"

Where can I set that time unit? In cProjects the value is set in project type...

Any idea?

Thanks!

Neil

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

Hi Neil,

Collaboration Projects -> Basic Settings -> Define Time Units

Check the document nearby, as it describes how (in which other customizing) should the Time Units in two system be set.

In the 'Define Project Types' you can maintain the default unit.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Zhenbo,

The customizing in RPM and ECC is the same on the time units definition, but still getting the error message:

TIME_UNIT/Time unit is empty in the controlling cockpit.

Where does the PS project take the time unit from?

Thanks

Neil

Konstantin
Participant
0 Kudos

Hi!

The PS project takes the time unit from project profile (SAP IMG -> Project System -> Structures -> Operative Structures -> Work Breakdown Structure -> Create Project Profile).

Please, check is all ok with it?

Regards, Konstantin Melnik

Former Member
0 Kudos

That was it.

Thanks Konstantin!

Answers (0)