Does anyone know what the following error is?

"Continuous I/O nodes not allowed for sequence-dependent setup activities"

Thanks

Rob

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rob - it sounds like you have components in the PDS with continuous cnsumption that are assigned to a setup activity. Check the material list in the recipe or the material components list in the phases. Make sure the components are assigned to production operations/phases.

Regards

Andy

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Andrew, good suggestion but everything looks good.

Thanks anyways

Former Member
0 Kudos

Hello,

Can you just check if the setup activity is to be picked from the setup matrix. That is PPM/PDS has a check indicator for sequence dependent setup activity and still you have standard values maintained for the setup activity.

Let me know if this works.