To activate multiple specification we had to delink MIC and class characteristic link. Because of this we are not able to move data from MIC to batch?

Any way out dears?

Regards

TOM

Accepted Solutions (1)

Accepted Solutions (1)

former_member42744
Active Contributor
0 Kudos

Yes.. in the plant settings in config, on the inspection completion tab, make sure the setting at the bottom of the page, "Batch valuation without material spec" is ticked on.

Craig

Former Member
0 Kudos

Craig

My understanding is that the link between MIC and batch characteristic should be there for movement of data from MIC to batch characteristic. In case of multiple specification i have to delink.

I am not sure as to how customizing will help in solving this issue.

Regards

TOM

former_member42744
Active Contributor
0 Kudos

Because that setting voids the need for the material spec link. As long as the MIC identified in the plan is linked to a general charac in the MIC master data, it will transfer the data.

I.e. it reads the MIC number in the plan, and goes and grabs the internal number for the general charac. If the general charac is on the batch, the value is transferred.

Craig