Progress Bar control

Former Member
0 Kudos

Hi all,

I m using SP15. In that i have used progress bar control. But it does not shows progress status. It shows only one color. I have defined both background and foreground color. But it shows background color only. Wat may be the problem?

Help me in this regard

Thanks & Regards

Hemalatha J

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

Yes you are Correct,

Progress bar will not work for Dynamic Expressions ,it is working for Static value .

if you given any value in its Default Value Filed then that value will be displayed in the Runtime.

I for dynamic Expression it will work in Future SPs .

Regards,

govindu