I had created a raw material with the lot size as 100. if i put purchase order for 40 it does not showing error can you help to create a lot size , i.e if i put purchase order less than 100 then it should throw me an error ......
thanx in advance
Hi,
Lot size in Material Master is for internal Production system where you Run MRP.. Your PO is for external purchases. Even if you maintain Lot size of 100, you can create PO of 10, 20 or what ever quantity.
Please Follow the link for LOT Size procedure,
http://help.sap.com/saphelp_40b/helpdata/en/7d/c27177454011d182b40000e829fbfe/content.htm
Hope this will help.
Reward Point if helpful.
Thanks,
Raja
Edited by: Raja Singh Chhabeda on Jun 26, 2008 12:04 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raja,
Ok i understand wat u said .Now i want to creater a external procurement how can i give the Lot-size . Will i able to give it ......
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In material master in MRP2 , Give procurement type F
and Lot size FS.
For Detail Configuration of Lot size Please Read the link and follow the steps as per your requirement,
http://help.sap.com/saphelp_47x200/helpdata/en/fe/819b9f643b11d3b4e40004ac160649/frameset.htm
Thanks,
Raja
hi,
we are not doing MRP run ...We want use fixed Lot -size.I have already gave the Lot-size in mm01 but if i give less than lot size it takes the value....Can u help to find it.......
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Joyshe,
We maintain Lot Size in MM01 its right, but this lot size is used for our Internal Production. When we want to produce material internally this lot size will come into picture. For example as you have maintained Lot size 100, if you will create Production order for Less than that it wont take,
Now, YOu are Creating Purchase Order for 40 Quantities, this quantity u wont produce internally, you are purchasing this, So u dont have any control in This.
Hope it is clear now.
Thanks,
Raja
Hi,
Lot size in Material Master is for internal Production system where you Run MRP.. Your PO is for external purchases. Even if you maintain Lot size of 100, you can create PO of 10, 20 or what ever quantity
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raj,
I had already specified my Lot-Size for the material while creating itself....... But also it is not showing error when i procure less than my Lot-size... wheather I need to specify my Lot-size any where else...Plz help me....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.