how to fix lot size

Former Member
0 Kudos

hi,

I had created a raw material with the lot size as 100. if i put purchase order for 40 it does not showing error can you help to create a lot size , i.e if i put purchase order less than 100 then it should throw me an error ......

thanx in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Lot size in Material Master is for internal Production system where you Run MRP.. Your PO is for external purchases. Even if you maintain Lot size of 100, you can create PO of 10, 20 or what ever quantity.

Please Follow the link for LOT Size procedure,

http://help.sap.com/saphelp_40b/helpdata/en/7d/c27177454011d182b40000e829fbfe/content.htm

Hope this will help.

Reward Point if helpful.

Thanks,

Raja

Edited by: Raja Singh Chhabeda on Jun 26, 2008 12:04 PM

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Raja,

Ok i understand wat u said .Now i want to creater a external procurement how can i give the Lot-size . Will i able to give it ......

Former Member
0 Kudos

Hi,

In material master in MRP2 , Give procurement type F

and Lot size FS.

For Detail Configuration of Lot size Please Read the link and follow the steps as per your requirement,

http://help.sap.com/saphelp_47x200/helpdata/en/fe/819b9f643b11d3b4e40004ac160649/frameset.htm

Thanks,

Raja

Former Member
0 Kudos

hi,

we are not doing MRP run ...We want use fixed Lot -size.I have already gave the Lot-size in mm01 but if i give less than lot size it takes the value....Can u help to find it.......

Former Member
0 Kudos

Hi Joyshe,

We maintain Lot Size in MM01 its right, but this lot size is used for our Internal Production. When we want to produce material internally this lot size will come into picture. For example as you have maintained Lot size 100, if you will create Production order for Less than that it wont take,

Now, YOu are Creating Purchase Order for 40 Quantities, this quantity u wont produce internally, you are purchasing this, So u dont have any control in This.

Hope it is clear now.

Thanks,

Raja

Former Member
0 Kudos

Hi,

Lot size in Material Master is for internal Production system where you Run MRP.. Your PO is for external purchases. Even if you maintain Lot size of 100, you can create PO of 10, 20 or what ever quantity

Thanks,

Raja

Former Member
0 Kudos

Hi Raj,

I had already specified my Lot-Size for the material while creating itself....... But also it is not showing error when i procure less than my Lot-size... wheather I need to specify my Lot-size any where else...Plz help me....

Lakshmipathi
Active Contributor
0 Kudos

Dear Joyshe

In material master MRP1 view, maintain FX for "Lot size" and retry the process.

thanks